Dylan 342a8f8382 Break v3 into 16 tickets
One file per feature, in the v2 shape that worked: goal, context, design,
implementation, acceptance criteria, tests, risks, out of scope -- written before
implementing so the risks are on paper rather than walked into.

Three carry more weight than their size suggests. V3-01 ships the port's first
real migration, and since the destructive fallback is gone, getting addColumn and
a v1-database test right matters more than the feature. V3-08 forces a
routing-engine decision with ongoing cost, so it sits behind a RoutingService
interface mirroring what LocationSource did for GPS. V3-13 is not code at all --
it answers the three questions open since v2, and V3-15 may close unbuilt as a
result, which is a legitimate outcome.

Several tickets record constraints that are easy to lose: no activity picker in
front of Start, because the founding premise is press-and-go with gloves; the
Route-to-Trip foreign key must not cascade, or deleting an old plan deletes the
ride; V3-14 will deliberately break the parity harness by adding GPX <type>, and
that expectation should be updated rather than the check dropped; and V3-16 must
not regress the explicit text colours that exist because of the black-on-black bug.

Co-Authored-By: Claude Opus 5 <noreply@anthropic.com>
2026-08-17 10:41:35 -05:00
..
2026-08-17 10:41:35 -05:00
2026-08-17 10:41:35 -05:00
2026-08-17 10:41:35 -05:00
2026-08-17 10:41:35 -05:00
2026-08-17 10:41:35 -05:00
2026-08-17 10:41:35 -05:00
2026-08-17 10:41:35 -05:00

v3 tickets

One file per feature, in the shape that worked for v2: Goal · Context · Design · Implementation · Acceptance criteria · Tests · Risks · Out of scope. Written before implementing, so the risks are on paper before they are walked into.

Menu, not a commitment. Nothing here is scheduled.

Everything in v3 is buildable with no server. Group rides, accounts and paid cloud backup are v4 — see ../BACKLOG.md.

Before starting anything: ../port/REAL-RIDE-CHECKLIST.md. The port has never recorded a real ride, and item I3 may still force a change of GPS engine — which would land underneath several of these tickets.

The tickets

# Ticket Size Depends on
V3-01 Activity type per ride M —
V3-02 Settings screen S —
V3-03 Distance and speed units S V3-02
V3-04 Live map on the recording screen M —
V3-05 Mounted (handlebar) mode M V3-04
V3-06 Live stats in the notification S —
V3-07 Route drawing (pins, straight lines) M —
V3-08 Road-snapped routing and ETA L V3-07, V3-01
V3-09 Follow a planned route M V3-04, V3-08
V3-10 Trip splitting S —
V3-11 Offline tile pre-download M V3-04
V3-12 Crash reporting S —
V3-13 Real-ride measurements M riding
V3-14 GPX interoperability S V3-01
V3-15 Auto-pause M V3-13 (gated)
V3-16 Visual identity M V3-04, V3-05

Dependencies

V3-01 ──┬────────────► V3-08 ──► V3-09
        └──► V3-14           ▲
V3-07 ──────► V3-08          │
V3-02 ──► V3-03              │
V3-04 ──┬──► V3-05 ──┬───────┘
        ├──► V3-11   └──► V3-16
        └──► V3-09
V3-13 ──► V3-15  (gate: may close unbuilt)

no dependencies: V3-01 · V3-02 · V3-04 · V3-06 · V3-07 · V3-10 · V3-12

Three that carry more weight than their size suggests

V3-01 ships the port's first real migration. The destructive fallback is gone, so getting addColumn plus a v1-database test right matters more than the feature does — V3-07 and V3-09 both add migrations behind it.

V3-08 forces a routing-engine decision with ongoing cost and vendor implications. Behind a RoutingService interface, mirroring what LocationSource did for GPS.

V3-13 is not code. It answers the three questions that have been open since v2, and V3-15 may close unbuilt as a result — a legitimate and probably likely outcome.

Suggested order, if starting cold

  1. V3-01 — proves the migration path while the stakes are low, and unblocks V3-08/14
  2. V3-02 + V3-03 — small, self-contained, gives V3-01 a home
  3. V3-04 — the most visible change, and the gateway to four other tickets
  4. V3-07 — entirely independent; useful on its own before the routing decision
  5. V3-13 — as soon as there is a ride to measure

V3-12 is a good filler at any point. V3-16 should wait until the screens stop moving.